Total capital cost is INR 14,447.64-crore under NH
(O).
The Cabinet Committee on Economic Affairs, chaired by the Prime Minister, Shri Narendra Modi, approved the development of a link/connector corridor between NH-19 and Varanasi Ring Road to ease traffic congestion in Varanasi city of Uttar Pradesh. It will provide connectivity along the banks of River Ganga.
The 46.039 km long project includes a six-lane
elevated main road, a magnificent 'cable-studded' bridge, 'Extradosed' Foot
Over Bridge-cum-Major Bridge, loops, ramps, link road, and service road. The
project will be completed under 'Hybrid Annuity Model' and through NH (O)
scheme with a total capital expenditure of INR 14,447.64-crore. This includes
civil construction cost of INR 6,037.85-crore (which includes utility shifting
but not including GST) and land acquisition cost of INR 541.11-crore.
The project will provide seamless connectivity
between NH-19 and Varanasi Ring Road, which will significantly decongest the
city's road network and facilitate urban mobility. Designed for a speed of
80–100 kmph, the project is expected to reduce the average travel time in the
area from about 60 minutes to 20 minutes, i.e., by about 67 per cent. The travel
time between NH-19 and Kashi Railway Station will also be reduced from about 50
minutes to 25 minutes.
In line with the PM GatiShakti National Master Plan,
it will strengthen multi-modal connectivity by providing high-speed
connectivity to major highways, railway stations, Lal Bahadur Shastri Airport,
and Ramnagar IWAI Port.
The project involves several significant engineering
features, including a magnificent 910-metre-long cable-stayed bridge over River
Ganga, a 1.32 km long Extradosed Foot Over Bridge-cum-Major Bridge with a
travelator seamlessly connecting pedestrians up to Kashi Vishwanath Temple, a
Rail Over Bridge over the existing/proposed Malviya bridge, dedicated parking
spaces for emergency use, soundproofing, facade lighting, and architectural
elements inspired from the cultural heritage of Varanasi.